After using Mobilinc for over a year I finally got round to setting up the resource manager. For some reason I cannot get it to work with scenes. The automatically generated programs in ISY contain the following (seemingly erroneous) lines in the 'if' clause, that never evaluate to true so the program never runs:
If
...
Status '[device in scene]' > Off
AND
Status '[device in scene]' < Off
Then

If I manually remove the "< Off" line the program will execute as expected.

Can you help?

Thanks.
- Paul

Re: Resource Manager Incorrectly managing scenes

PostPosted: Mon Apr 17, 2017 7:37 am
by AdminWes
Hi Paul,

For RM to work with scenes, the scene needs to have one of the devices be a scene controller.

If you can't get this working, please email us at support@mobilinc.com with a screenshot of your MobiLinc RM settings as well as a screenshot of your scene and all the devices in that scene from the Admin Console showing one of the devices as a scene controller.

Wes

Re: Resource Manager Incorrectly managing scenes

PostPosted: Mon Apr 17, 2017 10:29 am
by moggieuk
Screenshots sent. Thank you.